Full closure of Racine from Fullerton to Belden is necessary in multiple up- coming time frames in order to facilitate certain critical theatre school construction processes. The following dates and time frames has been scheduled for closure and confirmed with the Chicago Department of Transportation:

  • March 5th- 8am to 4pm for City of Chicago water main tap.
  • March 6th- 8am to 4pm for City of Chicago water main tap.
  • March 7th & March 8th- from 8am on the 7th through to approximately 8pm on the 8th for crane delivery and erection.
  • March 9th- 8am to 4pm, if necessary for restoration of street from water main work.
  • March 19th & March 20th- from 8am on the 19th through to approximately 8pm on the 20th for crane erection.

DePaul’s contractor has agreed to follow all proper closure procedures in accordance with the rules and regulations of the Department of Transportation, to include placement of appropriate barricades and signage.