Lincoln Park Sewer Main Project #7158

Updated: 3 days ago


Status: (In progress, sewer side only: 60%)


  • Schubert from Southport to Lakewood: mainline sewer installed, installation of catch basins completed.

  • Lakewood from Schubert to Wrightwood: mainline sewer installed; installation of catch basins and PDs still in progress.

  • Wayne from Schubert to 250 feet south: mainline sewer in progress; crews will continue laying pipes. There could be a possible interruption of gas and water services on the 2600 block of N Wayne only during working hours.


Lead Service Line Replacement program (water side) and PD corrective work will start after completion of sewer side.


Traffic Control: The intersection Schubert/Wayne will remain fully open. The 2600 block of N Wayne will remain closed and there will be limited parking on the street.


If you would like to receive regular email updates about the progress of this project, please go to BuildingANewChicago.org to register for project notifications. Simply enter your name, email address, and the project identification number (7158). By signing up for the project notifications, you will be informed as the project enters each new construction phase - from mobilization of equipment onto the site, to the installation of new pipes, to the final restoration of the street.