Milwaukee Avenue (North to Western) Street Reconstruction Update

Weather permitting, construction is tentatively scheduled to resume February 20th, pending clearance from and coordination with existing utilities. 


The remaining work will include bus pads, protective concrete bike medians installation, and striping.


During construction, temporary “No Parking” signs will be periodically installed as required for each activity listed above. These temporary signs will restrict parking during working hours, while adhering to rush hour restrictions, for the completion of the work. There will be significant impact on the traffic due to the nature of the work requiring one traffic lane to be temporarily closed near the construction activity. The contractor will provide extra flaggers and additional signs for bike traffic throughout the remainder of the project. All work on this corridor is estimated to be completed by May 16th.